General Information
- Project: Grupo Alcalá Oeste.
- Entity: Canal de Isabel II.
This WWTP had a capacity to treat 74,818 m3/d for a population of 374,090 inhabitants, but to adapt to the new legislation in force, the design flow was adapted to 59,000 m3/d, this is for an equivalent population of 280,250 inhabitants. In addition, the four lines of the existing biological reactor were remodeled, with a total volume of 15,547.2 m3, in a hybrid MBBR-Active sludge reactor