19.5km

long

NORWAY'S LARGEST TRANSPORTATION PROJECT TO DATE

The project consists of the longest twin rail tunnels in Scandinavia, connecting Oslo and Ski in Norway.

In the TBM (Tunnel Boring Machine) section of the Follobanen project, ACCIONA collaborated with the Italian company Ghella to execute what became the longest railway tunnel in the Nordic region and Norway’s largest transportation project. 

The TBM tunnel consists of two separate tunnel bores, each 18.5 km long with an internal diameter of 8.75 meters. It connects Oslo and Ski and has become a key section in the development of the Intercity network. The tunnel is designed for trains to travel at 250 km/h between the two cities and was excavated using four large double-shield TBMs. These TBMs were named “Anna from Kloppa”, “Magda Flåtestad”, “Queen Eufemia”, and “Queen Ellisiv”, in honor of four of Norway’s most courageous and pioneering women.

From the construction site at Åsland, located halfway between Oslo and Ski, where facilities for producing concrete segments and mass transport systems were established, the four TBMs began their journey. In a massive cavern, the TBMs—each 150 meters long and weighing 2,400 tons—were assembled and began excavation, with two TBMs heading toward Oslo and two toward Ski.

The challenging task of tunneling also involved blasting caverns for the TBMs, cross tunnels (including a 2.7 km-long escape tunnel), and two 420-meter-long transport tunnels. The joint venture between ACCIONA and Ghella also built the railway technical installations for the project, except for the signaling systems. 

The tunnel boring was completed in February 2019 when the last two TBMs reached Ski.

KEY ASPECTS

From the construction site at Åsland, located halfway between Oslo and Ski, where facilities for producing concrete segments and mass transport systems were established, the four TBMs began their journey. In a massive cavern, the TBMs—each 150 meters long and weighing 2,400 tons—were assembled and began excavation, with two TBMs heading toward Oslo and two toward Ski.

The challenging task of tunneling also involved blasting caverns for the TBMs, cross tunnels (including a 2.7 km-long escape tunnel), and two 420-meter-long transport tunnels. The joint venture between ACCIONA and Ghella also built the railway technical installations for the project, except for the signaling systems. 

The tunnel boring was completed in February 2019 when the last two TBMs reached Ski.

GENERAL INFORMATION

  • Location: Oslo, Norway
  • Contract type: EPC (Engineering, Procurement, and Construction)
  • Infrastructure: Dual-bore railway tunnel, each bore 18.5 km long with an internal diameter of 8.75 meters, excavated through rock using four double-shield TBMs.
  • Project delivery: 2023
  • Objective: To halve travel time between Oslo and Ski from 22 to 11 minutes.
  • Benefit: Economic development in the region and improved communication between Oslo and Ski.
  • Milestone: Upon completion, this became the longest railway tunnel in the Nordic region.

ENVIRONMENTAL IMPACT MANAGEMENT

One of the priorities of the AGJV consortium whilst the project is being carried out has been to minimise the environmental impact.

  • AGJV used conveyor belts to move rock debris to the workplace in Åsland and eliminated the need for thousands of vehicle trips to complete the same task, avoiding the emission of more than 27,000 tonnes of CO2 during tunnel drilling.
  • AGJV has reused 75 % of the excavation material for the preparation of the so-called deposit area where Oslo City Council will subsequently undertake urban development.
  • In collaboration with ACCIONA, a complex tunnel water treatment system was designed that includes the addition of ferrous sulphate to the circuit, allowing the management of incoming water from the simultaneous excavation of 4 TBMs, with a discharge of approximately 200-250 m3/h, high pH and TSS values as well as high hexavalent chromium (CrVI) content. The chromium action plan implemented in the WTP has allowed the reduction of CrVI by 75 %. The treatment of water in the project has also allowed the reuse of water (more than 80 %) in work activities, minimising the consumption of natural resources.
  • Monitoring is carried out in order to meet both ACCIONA and the client's sustainability requirements during the execution of the work. This monitors, among other aspects, the consumption of energy and materials, prioritising the use of materials with EPD (developing it where necessary, in collaboration with ACCIONA's R&D department), certified timbers and using machinery with high environmental standards.

Project implementation complies with all of Norway's strict environmental laws and regulations, as well as with the corporate objectives of the National Railway Administration of Norway.

RELATIONSHIP WITH THE COMMUNITY 

To observe how the largest railway tunnel in Scandinavia is being built, with work due to be finalised in 2021, since 2017 Oslo has had a visitor centre that provides detailed information on the particularities of the design and construction process. Citizens can see the difficulties of this ambitious project and how its various phases are being carried out, with audio-visual material, illustrations, documentation and 360-degree projections of the tunnel under construction.

ACCIONA's Engineering Business Line led the execution project as the main designer.

Technology and innovation

To design the concrete used for the tunnel reinforcement keystones, on the one hand a comparison of short fibres, both polymeric and steel, was carried out to optimally meet the requirements of residual resistance to flexotractions.

On the other hand, it was proposed, through a detailed study, to replace the tunnel of thermal curing of the keystones with the use of latest generation accelerating additives based on CSH gels.

 

At the same time, the productivity of the tunnelling machine has a significant financial impact on the project budget. This is why we worked with the Data Science team at ACCIONA's Digital Innovation Hub to develop a model that would predict critical stops with impact on the project, by analysing the machines' sensors.

 

At ACCIONA we face the challenge of making a predictive model that would improve machine productivity by studying engine failures to increase the time it is operational. Therefore, all the engine faults during different parts of the production were sought.

 

The model has been able to predict faults, with great precision, even up to 15 days in advance. The predictive technology developed will be used in the next tunnels to prevent critical engine failures.

 

Furthermore, the design and construction of a new contact line allows, among many advantages, to adapt to the space limitations due to the small diameter of the tunnels without having to reduce the maximum speed of the trains, increasing efficiency and security with respect to the current systems.

    Awards and recognitions

    The project has won and been a finalist in several international awards:

    Want to know more about TBMs?

    The machine that even Jules Verne was unable to imagine

    The technological evolution of tunneling machines, which accelerated at the end of the 19th Century and finally took off in the first half of the 20th, contributed greatly to the expansion of land transport worldwide. The excavation of tunnels to break through mountain ranges or circumvent difficult passes facilitated the ferrying by rail and road of passengers and freight, with their subsequent social and economic benefits...

    Discover other projects

    All of our projects