76km

of road

Construction, refurbishment, reclamation and conservation

Concession for the construction, renovation, restoration and conservation of an existent shadow toll road measuring 76.50 km long, in the section between the Ring road 2 (Guadalajara) and the provincial border with Soria.

In the 76.50-km section, the A-2 motorway is the main artery of the Spanish road network, linking the cities of Madrid and Barcelona.

The works in the road were classified according to the following three areas:

  • Area 1: Renovation and first set-up.
  • Area 2: Replacement works and intensive repair.
  • Area 3: Operation works and maintenance of the road.

The concession will be completed in 2026.

GENERAL INFORMATION

  • Location: Aragón, Spain.
  • Contract type: Construction, remodelling, restoration, operation and maintenance.
  • Infrastructure: Rehabilitation and maintenance of existing A-2 road measuring total length of 76.50 km.
  • Year of project completion: 2009